Work Completed:
- The new water mains on Van Buren and on Chicago Street, south of Van Buren were pressurized and chlorinated for testing
- The contractor completed installation of the new water main through the former surface parking lots
- Installation of the new 12” water main north to Clinton Street began
- The replacement of the sanitary sewer main in the middle of Chicago Street was completed to just south of Clinton Street
- The new sanitary sewer services were installed to Clinton Street
Activities to occur week of September 16:
- Pending approved chlorination samples, water service replacements will begin on Van Buren Street and then on Chicago Street from Jefferson moving north
- The 12” water main installation will be completed to the south side of Clinton Street
- The new water mains in the City Square and on Chicago Street between Van Buren and Clinton will be pressurized for testing
- Storm sewer installations will begin at the south end of the project near Jefferson Street
- Com Ed crews will be excavating and adjusting below ground ducts at Clinton & Scott Streets
- Daytime lane closures can be expected at Chicago & Clinton, and at Clinton and Scott Streets
Water Main Installation in the Surface Parking Lot
|